PIONEER continues construction of the OPUS club residence. Monolithic work on the foundation slab is 80% complete, and the car park cover slab is 55% complete. Works on erection of vertical structures of the ground floor continue, reinforcement of the ground floor slab in the area of the 6th section has started.
At the construction site of the business centre, earthworks are 85% complete, whereas the sub-concrete base and waterproofing of the foundation slab are 55% complete. The foundation slab is 40% complete.
All works are being carried out in accordance with the project schedule.