OPUS: Faсade Glazing Underway

At the OPUS club residence, 50% of the faсade substructure for glazing has been completed. Faсade glazing has commenced on sections 5 and 6. Installation of lift systems is nearing completion in the final section. Intensive work is ongoing on all MEP systems in both the underground and above-ground parts of the building. Waterproofing of the podium is 75% complete. In the OPUS business centre, finishing work on technical rooms in the underground section is almost finished.

This elite project by PIONEER on Derbenevskaya Embankment includes a club residence, business centre, and a retail gallery that will feature fine dining restaurants, boutiques, beauty salons and more.