As of May, 60% of the façade substructure for glazing has been installed at the OPUS club residence. Façade glazing continues in sections 1, 2, 5, and 6.
Elevator installation is nearing completion. Engineering systems are being installed throughout both the underground and above-ground parts of the building. Waterproofing of the rooftop is 90% complete. The courtyard’s stylobate waterproofing is 80% complete, and the first groundwork layers for landscaping have begun.
Technical rooms in the basement level of the OPUS business centre are also nearing completion.