2023.08.02

The heat network has been removed from the OPUS business centre construction site

Active zero-cycle construction works continue on the club residence and business centre OPUS site. The general contractor is carrying out concrete preparation on an area of about 3 000 m² for the construction of the club residence. The waterproofing continues: in the near future, workers will start the reinforcement framework of the foundation slab.

On the plot for the OPUS business centre, the removal of the heating network from the construction site has been completed. The sheet pile fencing of the excavation is 50% complete, and 25% of the excavation work has been completed.

Construction of the facilities is proceeding following the schedule.

Choose